Annex A: 1-bed social housing flats illustrative/potential supply pipeline
Source |
Number in period 2024-29 |
Potential Housing First availability |
Notes |
Housing Development Programme new-build |
31 |
8 |
25% of planned ‘baseline’ supply |
S106 provision |
95 |
23 |
25% of planned ‘baseline’ supply |
Use of commuted sums / Right to Buy receipts |
75 |
75 |
Acquisition programme |
Bell Farm refurbishment |
10 |
10 |
Based on local letting plan with no more that 25% Housing First use of total 40 flats provided |
Other delivery routes |
39 |
39 |
|
Existing CYC stock – direct lets |
890 |
445 |
Estimated 178 1-bed lets per year – applied 50% for HF |
Total |
1,140 |
600 |